California’s New Private Works Claims Process: Why Owners and Contractors Must Update Their Agreements
California has rewritten the rules for resolving payment and change-order disputes on private construction projects. Senate Bill 440, the Private Works Change Order Fair Payment Act, was enacted as Chapter 583 of the 2025 Statutes and is codified at California Civil Code section 8850 (Cal. Civ. Code § 8850 (West)). It applies to most private construction contracts entered into on or after January 1, 2026 (Cal. Civ. Code § 8850(n) (West)). The Act creates a mandatory, structured claims process with strict deadlines, interest penalties and work-suspension rights, none of which can be waived. As 2026 projects mature and claims begin to accrue, these procedures will move from the statute book to the jobsite.
One feature at the outset shapes everything else: the Act sunsets. By its terms, the article remains in effect only until January 1, 2030, when it is repealed (Cal. Civ. Code § 8851 (West)). Until then, it governs — and it governs on terms no contract can override.
What the Act Covers and What It Does Not
The Act reaches most private works of improvement, but its exclusions matter. It does not apply to a residential project that is not mixed-use and does not exceed four stories (Cal. Civ. Code § 8850(o) (West)). Just as important, the statutory definition of “owner” excludes public entities — state agencies, cities, counties, districts and the like — so the Act is a private-works regime; public projects remain governed by their own claims statutes (Cal. Civ. Code § 8850(c)(2)(B) (West)). The Act arrived alongside a companion 2025 reform that reduced permitted retention on most private works projects from 10% to 5%; owners and contractors updating their forms should address both changes together.
The Non-Waivable Core — With Two Deliberate Exceptions
Any waiver of the rights the Act grants is void and contrary to public policy (Cal. Civ. Code § 8850(m)(1) (West)). The familiar strategy of drafting proprietary claims language into an owner-favorable contract to displace these rights no longer works.
But “non-waivable” is not “untouchable,” and the two carve-outs are central to updating agreements:
- The parties may agree, in writing, and after a claim is made, to skip the informal conference and mediation and proceed directly to litigation or binding arbitration ( Civ. Code § 8850(m)(2)(A) (West)).
- The parties may also agree to reasonable additional change-order, claim and dispute-resolution procedures — so long as those provisions do not conflict with or impair the statute’s timeframes and processes ( Civ. Code § 8850(m)(2)(B) (West)).
The second exception is the drafting lane. Agreements should be revised not to override the Act but to layer compatible, workable procedures on top of it.
How the Process Works
Contractors must serve claims a specific way. The Act defines a “claim” as a demand — sent by registered or certified mail, return receipt requested — for a time extension, additional compensation or payment of a disputed amount (Cal. Civ. Code § 8850(c)(1) (West)). The Act also channels subcontractor pass-through claims through the general contractor; the contractor must notify the subcontractor in writing within 30 days whether it submitted the claim and must act in good faith throughout (Cal. Civ. Code § 8850(j)(3)(B), (j)(4) (West)).
Owners face hard deadlines backed by penalties. Once a claim is received, the owner must issue a written statement within 30 days identifying disputed and undisputed amounts (extendable only by mutual written agreement) and must pay all undisputed amounts within 60 days of that statement (Cal. Civ. Code § 8850(d)(1)(A), (d)(2)–(3) (West)). Missing these deadlines triggers interest of 2% per month, 24% annually (Cal. Civ. Code § 8850(h)(1) (West)). Disputed amounts later found to be owed carry the same 2% monthly interest, running from the date they would have been due absent the dispute (Cal. Civ. Code § 8850(h)(2) (West)).
Meet-and-confer and mediation come before litigation. If the contractor disputes the response or the owner fails to respond, the contractor may demand an informal meet-and-confer conference, which the owner must schedule within 30 days (Cal. Civ. Code § 8850(e)(1)–(2) (West)). Within 10 business days after the conference concludes, the owner must issue a further written statement and pay any newly undisputed amounts (again within 60 days) (Cal. Civ. Code § 8850(e)(3)–(4) (West)). Remaining disputes go to nonbinding mediation, with costs shared equally; the parties have 10 business days to agree on a mediator, and if they cannot, the contractor gets to select one — a trap for owners who let the clock run (Cal. Civ. Code § 8850(f)(1)–(3) (West)). Only after mediation fails may the parties proceed to the dispute-resolution mechanism in their contract (Cal. Civ. Code § 8850(f)(4) (West)).
Non-response has teeth, but is not a merits loss for the contractor. An owner’s failure to respond within the statutory windows deems the claim denied in its entirety (Cal. Civ. Code § 8850(g)(1) (West)). Critically, that deemed denial is not an adverse finding on the merits of the claim; it simply opens the contractor’s remedies, including work suspension (Cal. Civ. Code § 8850(g)(2) (West)).
Nonpayment can stop the job. If an owner fails to pay or otherwise comply, the contractor (or subcontractor) may suspend work without penalty by following two steps: written notice, by registered or certified mail, that payment is due; and, 30 days later, a further 10-day written notice of intent to stop work, sent the same way (Cal. Civ. Code § 8850(k)(1)–(2) (West)).
What Owners and General Contractors Should Do Now
Because the Act overlays — and can override — contract terms, the answer is not to draft around it but to align agreements and internal practices with it, using the statute’s additional reasonable procedures allowance (Cal. Civ. Code § 8850(m)(2)(B) (West)). Key steps are:
- Conform contract claims provisions to the statute. Update notice, response and payment clauses so that they mirror the Act’s 30-day response, 60-day payment, meet-and-confer and mediation sequence rather than conflict with it.
- Remove void overrides; add only compatible procedures. Strike any language purporting to waive, shorten or supplant these rights and confirm that any supplemental procedures you keep do not impair the statutory timeframes ( Civ. Code § 8850(m)(1), (m)(2)(B) (West)).
- Decide the arbitration/litigation off-ramp in advance. Because the parties may agree in writing to bypass the conference and mediation, consider whether your standard form should tee up that election and specify the downstream forum ( Civ. Code § 8850(m)(2)(A) (West)).
- Fix the service and notice mechanics. Ensure notice provisions accommodate registered or certified mail, return receipt requested and reconcile any tension with the contract’s own notice terms ( Civ. Code § 8850(c)(1) (West)).
- Build in the calendar. Owners should establish internal claims-handling procedures that guarantee a written response within 30 days and payment of undisputed amounts within 60 days and should be realistic early about what is genuinely undisputed to avoid interest and work stoppages.
- Mind the mediator-selection deadline. Calendar the 10-business-day window to agree on a mediator so the owner does not forfeit that choice to the contractor ( Civ. Code § 8850(f)(2), (f)(3)(A) (West)).
- Train the project teams. Both sides should train personnel on the strict timing and service requirements — contractors to preserve remedies, owners to avoid penalties.
Bottom Line
The Act standardizes how private construction claims are presented, evaluated and escalated, and it does so on terms no contract can override. However, it deliberately leaves room for compatible, agreed procedures (Cal. Civ. Code § 8850(m)(1), (m)(2)(B) (West)). The penalties for noncompliance are steep, the interaction between statute and contract is complex, and every response in the process may later become evidence. With the Act in force now and set to run through 2030, owners and general contractors should revise their agreements and internal procedures and involve counsel in crafting the language and documentation, rather than wait for the first 2026 dispute to test them (Cal. Civ. Code § 8851 (West)).