Additional Mobilization and Demobilization
The cost of extra demobilizations and remobilizations resulting from Government-caused delay are recoverable. In Marlin Associates, Inc., GSBCA No. 5663, 82-1 BCA 15,739 (1982), the Board held that the contractor was entitled to be compensated for the cost of an extra mobilization and demobilization, including overhead and profit. The Board noted that the contractor’s price included only a first mobilization and final demobilization. Therefore, contractors are entitled to recover for the extra demobilization and remobilization.
Updated: July 24, 2018
Looking for additional government contracting resources?
Search Our Database
Cherylyn Harley LeBon
Chair
Meet Our Team
Government Contracting Database
Related Capabilities
Government Contracting Compliance Contract Negotiation and Formation Dispute Resolution: REAs, Claims, and Terminations Dredging Federal Construction Contracting Federal Contract Administration Protests Small Business Procurement State and Local Government ContractingNews and Publications
March 30, 2026
/
Cohen Seglias
New Executive Order Issued Related to Diversity, Equity and Inclusion
January 5, 2026
/
Cohen Seglias
DoD Cybersecurity: The Government Continues Its Enforcement Effort
November 17, 2025
/
Executivegov.com
Cherylyn Harley LeBon Among Experts Providing Advice During Government Shutdown