    Lump Sum or Unit Price in Federal Contracts

    In federal contracts, the preference is for lump sum pricing. However, in certain instances, unit price contracts are appropriate. Those instances are described in the Federal Acquisition Regulations at Section 36.207, which states:

    Lump sum pricing shall be used in preference to unit pricing except when:

    1. Large quantities of work such as grading, paving, building outside utilities, or site preparation are involved
    2. Quantities of work, such as excavation, cannot be estimated with sufficient confidence to permit a lump-sum offer without a substantial contingency
    3. Estimated quantities of work required may change significantly during construction
    4. Offerors would have to expend unusual effort to develop adequate estimates

    (emphasis added)

    Updated: July 24, 2018

    Looking for additional government contracting resources?

    Search Our Database

    Capabilities

    Cohen Seglias
    Privacy Overview

    This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.