linkedin linkedin
twitter twitter
facebook facebook
youtube youtube
30 Years in Business
Learn more About Us
Browse by Last Name
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z
    July 1, 2019 / Publications
    DC Enacts New Paid Leave Requirements

    Government Contracting Database

    Increased Labor Costs

    Where a contractor’s work or part of its work is delayed by the government, the direct increased labor costs are a compensable element of the contractor’s delay claim. Excavation-Construction Inc., ENGBCA No. 3858, 82-1 BCA ¶ 15,770 (1982); United States Steel Corp. v. Missouri Pacific R.R. Co., 668 F.2d 435 (8th Cir. 1982). Such increased labor costs include increases in wage rates. See, e.g., J.D. Hedin Constr. Co. v. United States, 347 F.2d 235 (Ct. C1. 1965) (when project shifted into a period of higher wage rates as a result of owner-caused delays, contractor has not accepted risk and owner held liable for risk); Garcia Concrete, Inc., AGBCA No. 78-105-4, 82-2 BCA ¶ 16,046 (1982) (55-cent wage rate increase awarded on work that would have been done before the effective date of the increase but for owner’s delay). The Board in Sydney Constr. Co., ASBCA No. 21377, 77-2 BCA ¶ 12,719 awarded such damages, stating:

    We do agree that the work ultimately performed in-June through August 1975 would have been performed from March through June 1975 at which time performance would have been completed but for the government delay. Accordingly, for the 75-day delay which we have found previously, we find appellant entitled to recover the increase in wage rates paid during the period of extended performance.

    Updated: August 2, 2018

    Capabilities